SP060010C8253 Federal Contract Award

Agency code 97AS

THIS MODIFICATION PROVIDES AN EQUITABLE ADJUSTMENT FOR COSTS TO REPLACE EXISTING CONDUIT AND SWITCHGEAR IN PERFORMANCE OF PROJECT XLWU203045, ZONE 4 INFRASTRUCTURE PHASE 1.

02 / Contract Size and Status

What is the recorded size and timing of this contract?

Net obligations$295.16M
Contract actions228
Potential value-$2.12M
Latest actionMay 18, 2026
Effective dateSep 28, 2010
Completion dateMay 31, 2061
NAICS markets1
PSC categories1

03 / Spending Trend

SP060010C8253 contract spending by fiscal year

Annual net obligations across the complete period available for this agency and PIID, from the first recorded fiscal year through the latest contract action.

Latest fiscal year obligations$9.35M
FY 2026
Net obligationsComplete recorded range
Fiscal yearNet obligationsActionsChange
FY 2010$901.3K1
FY 2011$3.82M5+324.3%
FY 2012$3.04M5−20.5%
FY 2013$2.44M6−19.9%
FY 2014$4.87M9+99.9%
FY 2015$2.70M8−44.6%
FY 2016$4.71M9+74.9%
FY 2017$2.48M13−47.4%
FY 2018$7.87M13+217.8%
FY 2019$11.24M18+42.8%
FY 2020$11.12M11−1.1%
FY 2021$14.83M22+33.4%
FY 2022$182.70M34+1,131.7%
FY 2023$12.47M23−93.2%
FY 2024$6.57M25−47.3%
FY 2025$14.05M20+113.8%
FY 2026$9.35M6−33.5%

04 / Federal Buyer

Which organization manages this contract?

DepartmentContracting agencyContracting office
DEPT OF DEFENSEDEFENSE LOGISTICS AGENCYDLA ENERGY

05 / Contractor

Who holds this federal contract?

GULF COAST ELECTRIC COOPERATIVE, INC.

UEI XWMELMCAHAM4 · CAGE 3EU42

06 / NAICS Industries

Which industries classify this contract?

CodeDescriptionObligationsActionsShare
221122ELECTRIC POWER DISTRIBUTION$295.16M228100.0%

07 / Products and Services

What products or services were purchased?

CodeDescriptionObligationsActionsShare
S112UTILITIES- ELECTRIC$295.16M228100.0%

08 / Place of Performance

Where is the work recorded?

TYNDALL AFB, BAY, FLORIDA, UNITED STATES

ZIP 324035022

09 / Contract Actions

What modifications and obligations were recorded?

Signed dateModificationObligationContracting officeNAICSPSC
May 18, 2026P00227-$2.12MDLA ENERGYOffice code SP0600221122S112
Apr 13, 2026P00226$0DLA ENERGYOffice code SP0600221122S112
Mar 23, 2026P00225$888.4KDLA ENERGYOffice code SP0600221122S112
Mar 19, 2026P00224$10.55MDLA ENERGYOffice code SP0600221122S112
Feb 10, 2026P00223$20.2KDLA ENERGYOffice code SP0600221122S112
Jan 5, 2026P00222$0DLA ENERGYOffice code SP0600221122S112
Dec 8, 2025P00221$422.8KDLA ENERGYOffice code SP0600221122S112
Nov 18, 2025P00220$5.86MDLA ENERGYOffice code SP0600221122S112
Nov 3, 2025P00219$104.9KDLA ENERGYOffice code SP0600221122S112
Oct 27, 2025P00218$105.5KDLA ENERGYOffice code SP0600221122S112
Sep 17, 2025P00216$240.5KDLA ENERGYOffice code SP0600221122S112
Sep 17, 2025P00217$68.3KDLA ENERGYOffice code SP0600221122S112
Sep 16, 2025P00215-$595DLA ENERGYOffice code SP0600221122S112
Sep 3, 2025P00214$85.9KDLA ENERGYOffice code SP0600221122S112
Sep 2, 2025P00213$3.87MDLA ENERGYOffice code SP0600221122S112

10 / Reading the Contract

How should this award record be interpreted?

Read the PIID as a transaction history, not as a single purchase price. Net obligations combine the base action with later increases, reductions, corrections, and deobligations recorded under the same contract.

01

Verify the buyer

Agency and office identify who manages the procurement relationship.

02

Follow modifications

Each action can change funding, scope, dates, or administrative terms.

03

Compare the market

Use NAICS, PSC, and the contractor profile to identify related buyers and competitors.